    Agricultural Engineering : Surveying And Levelling

1.

The object of surveying is to prepare a

A.  Drawing
B.  Cross section
C.  Map
D.  None of the above

2.

The main principle of surveying is to work from

A.  The center of the boundary
B.  The whole to the part
C.  Both
D.  None of these

3.

The walking step of a man is considerd equal to

A.  80 cm
B.  70 cm
C.  60 cm
D.  50 cm

4.

compensating error is proportional to

A.  L1/2
B.  L1/3
C.  L1/4
D.  L1/5

5.

The survey stations are located on the ground by

A.  Reference sketch
B.  Imaginary sketch
C.  Horizontal sketch
D.  None of the above